Schedule News
My installer finally returned my e-mail today. He’s picking up the sealed electrical and building plans from his engineer today. He’ll be submitting the permit application next week. The permit application should take 3-4 weeks.
That puts installation in mid-April, instead of mid-March as he originally stated.
After installation, we contact PSE&G to come out and test and certify the equipment. It’s at that point that PSE&G will replace the meter. Once they certify the system we can fire it up for real. There might be one more visit after that – the state Board of Public Utilities will come and check the paperwork and PSE&G approval sticker before paying out the rebate.
Comments
Tell me what you're thinking...
and oh, if you want a pic to show with your comment, go get a gravatar!