Schedule News

February 27, 2004 by
Filed under: Solar Energy 

My installer finally returned my e-mail today. He’s picking up the sealed electrical and building plans from his engineer today. He’ll be submitting the permit application next week. The permit application should take 3-4 weeks.

That puts installation in mid-April, instead of mid-March as he originally stated.

After installation, we contact PSE&G to come out and test and certify the equipment. It’s at that point that PSE&G will replace the meter. Once they certify the system we can fire it up for real. There might be one more visit after that – the state Board of Public Utilities will come and check the paperwork and PSE&G approval sticker before paying out the rebate.